Petromium Tools / Formula set COST-NPT-001
Drilling Cost & NPT Tracker
Activity timeline · spread accrual · explicit NPT attribution · SPE bit-run audit· V2.0
Animated reconciliation
Rig-time, cumulative cost, and NPT Pareto
Rig-time ribbon
Direct user classification · gaps stay unclassified
24 h
Operating
19 h
NPT
5 h
Excluded
0 h
Unclassified
0 h
Cumulative cost
Actual accrual · linear budget reference
USD 320k
NPT cause Pareto
Review · not an approval
Reporting-window status
Actual report cost
USD 320,000
Attributed NPT cost
USD 76,958
NPT / counted
20.83%
Budget variance
USD 20,000
Timeline, rates, and costs remain separate
Drilling cost and NPT worksheet
Activity timeline
Overlaps are blocked. Gaps remain unclassified. Time class and plan status are deliberately independent.
Time-rate cost components
Multiple components may overlap. Switching day/hour basis preserves the same effective hourly rate.
Direct cost ledger
A direct cost becomes NPT-attributed only when linked to an explicitly NPT-classified activity.
SPE PEH bit-run comparison
Independent Eq. 11.1 relationship; no bit or drilling-practice recommendation is made.
Calculated: USD 16,150 total · USD 14.04 per ft
Calculation complete
Calculation audit
Report hours
24 h
Counted hours
24 h
Entered drilled
450 ft
All-in cost / ft
USD 711.11
Time-rate cost
USD 235,000
Direct cost
USD 85,000
Calculation observations
NPT, plan status, cause, and responsibility are direct user classifications; the tool does not infer company policy, root cause, or liability.
The loaded values are a reference example only and must be replaced with controlled DDR, tour-sheet, cost, AFE, and contract records.